Quick Answer: Estimate total labor hours as measured quantity × person-hours per unit, then add any separately allowed labor hours. Multiply those hours by the applicable loaded hourly labor cost. In this guide, loaded labor means wages plus employer labor burden; job overhead and company overhead are separate cost pools, added once. Use separate rates when the work involves different trades or pay grades.

Key Takeaways

  • Quantity × person-hours per unit = person-hours. Person-hours × cost per person-hour = labor cost.
  • A crew-hour is elapsed time for a whole crew. Two people working four hours use eight person-hours.
  • Define what your labor rate and productivity allowance already include before adding other costs.
  • Recover each labor, job-overhead and company-overhead cost once. A percentage markup on cost is not the same as a margin on selling price.

Start with quantity and person-hours

Measure the scope in a consistent unit, such as installed fixtures or square feet. Use comparable completed jobs to estimate person-hours per unit, noting crew composition, access, work conditions and the tasks included. Multiply that rate by the current quantity. If your records instead show units per crew-hour, divide quantity by that output to get elapsed crew-hours, then use the total hourly cost of every crew member.

Keep the units consistent. Multiplying hours per unit by an hourly labor cost gives a cost per unit; multiply by quantity to obtain a total. Record whether setup, material handling, cleanup and supervision are already included in the productivity allowance. Add them separately only when they are excluded.

Define the loaded labor rate

For this example, loaded labor cost is the employee's wage plus employer labor costs allocated per person-hour. Depending on the employer's actual obligations and records, those costs may include employer payroll taxes, workers' compensation and employee benefits. Use the applicable payroll records, insurance information and benefit costs; this article supplies no tax rates or standard burden percentage. Match the rate's paid-hour or chargeable-hour basis to the hours in your estimate.

Here, that labor rate excludes job overhead and company overhead. Some estimating systems use the word “burden” more broadly. If your rate already includes either overhead pool, identify the included amount and do not add it again. Likewise, a purchased unit-price item may already contain tasks or employer costs: Gordian's Construction Task Catalog introduction documents the labor costs and activities included in its particular unit prices. Check the applicable catalog and contract instead of assuming its inclusions match yours.

Keep job overhead and company overhead separate

The USACE Japan Engineer District's November 2024 estimating guide, sections 02.2.6.2.2 and 02.2.6.2.3, distinguishes job or field-office overhead from home-office overhead. Its project rules are specific to that district; the useful principle here is to document the cost pools and their calculation basis.

Cost poolExample contentsDouble-count check
Direct wagesPay for the person-hours assigned to the workDo not repeat the same hours in another allowance.
Employer labor burdenEmployer-paid labor costs allocated to those hoursCheck whether the hourly or catalog rate already includes them.
Job overheadIdentified temporary site facilities, utilities or project supportExclude costs already in labor, equipment or another project line.
Company overheadAn allocation of office and business administration costsState the allocation method and exclude costs already charged to this job.
Pricing allowanceThe amount added above the defined estimated cost baseState whether the chosen percentage is markup on cost or margin on price.

Supervision, mobilization and cleanup can sit in different cost pools depending on the estimating method. Choose one location for each cost and document it. An overhead percentage has meaning only when its base and included costs are stated.

Worked example: a hypothetical labor-only package

The figures below are invented teaching inputs, not wage, insurance, tax, productivity or profit benchmarks. Assume 200 identical installed units, all workers at the same hourly cost, and 0.4 person-hours per unit for installation only. The additional eight person-hours cover setup and cleanup excluded from that productivity figure. The hourly wage and burden amounts use the same hour basis.

StepCalculationResult
Installation labor200 units × 0.4 person-hours/unit80 person-hours
Setup and cleanupSeparately assumed; excluded above8 person-hours
Total labor hours80 + 888 person-hours
Direct wages88 × $30/person-hour$2,640
Employer labor burden88 × $10/person-hour$880
Loaded labor total88 × ($30 + $10)$3,520
Job overheadAssumed site-facility and utility charges, separate from labor$480
Company overhead allocationAssumed office-cost allocation, separate from job overhead$400
Defined estimated cost base$3,520 + $480 + $400$4,400

The $10 burden includes neither overhead pool. The $480 and $400 contain none of the wages or employer costs already included in the 88 labor hours. This example excludes materials, equipment, sales tax, bonds and contingency; it is not a complete construction bid. Add any required excluded scope using its own documented basis before pricing a real job.

Markup and margin use different denominators

For the same defined cost base C and proposed price P, markup = (P − C) ÷ C, while margin = (P − C) ÷ P. Business Victoria's margin and markup guide explains the different denominators and distinguishes gross from net measures. Because this example includes an allocation of company overhead, the percentage below is simply margin above this defined estimated cost base, not a claim about accounting gross or net profit.

  • A hypothetical 25% markup gives $4,400 × 1.25 = $5,500. The amount above the defined costs is $1,100, or 20% of the price.
  • A hypothetical 25% margin on price requires $4,400 ÷ (1 − 0.25) = $5,866.67, rounded to cents. The amount above the defined costs is $1,466.67; rounding makes the ratio approximately 25%.

Those percentages illustrate arithmetic, not a recommended price or guaranteed return. Actual hours, costs, excluded scope and collection outcomes can change the result.

Compare self-performed work and subcontract quotes on the same scope

Compare your complete self-perform estimate with the subcontract quote plus the costs you would still incur if you subcontracted. Check quantities, materials, equipment, supervision, cleanup, exclusions and schedule obligations on both sides. Identify company-overhead recovery separately and allocate it once under your chosen method. A labor-only internal figure and an all-in subcontract quote are not directly comparable.

Check the estimate before sending it

  1. Record the quantity, unit, drawing revision and included tasks.
  2. Confirm whether the productivity rate uses person-hours or crew-hours and whether it includes non-installation time.
  3. List the wage and employer-cost basis for each labor rate; avoid applying another burden factor to an already loaded rate.
  4. List job overhead and company overhead separately, marking any amount already recovered elsewhere.
  5. State the cost base used for markup or margin, and document excluded scope and any separate risk allowance.
  6. After the job, compare estimated and actual quantities, hours and costs using the same categories.

Frequently Asked Questions

What is a burdened labor rate?

In this guide it is wages plus employer labor costs per person-hour, excluding job and company overhead. Other systems may include more costs in “burden”; check the rate's definition and recover each cost only once.

How do I estimate productivity?

Use comparable completed jobs and state the unit, crew composition, site conditions and included tasks. Distinguish person-hours per unit from units per elapsed crew-hour before multiplying by a labor rate.

What labor hours do estimators forget?

Check setup, material handling, cleanup, supervision and closeout work. Add hours separately only if the same work is not already included in the productivity rate or another cost line.

Build your estimate from reviewed quantities

Review your PDF takeoff quantities, then apply your own labor rates and productivity assumptions.