CyanBuild

How to Create a Schedule of Values in Construction

A schedule of values is the financial backbone of every progress billing on a commercial job. Get it right and your pay applications flow. Get it wrong and you fight for every dollar.

A schedule of values, or SOV, is the line item breakdown of the total contract sum that a contractor submits to the architect and owner before the first pay application. Each line represents a portion of the work, priced as a scheduled value, that gets reported as partially complete on each AIA G702 Application for Payment. The SOV is how the team agrees up front on what each piece of the project is worth, so that progress billing becomes a measurement exercise rather than a negotiation every month.

What a Good Schedule of Values Contains

Every line on the SOV ties to a real piece of work. The cleanest schedules follow the specification divisions, so the math lines up with the estimate and the buyout. A typical commercial SOV breaks the job into 20 to 60 lines, each with a number, a short description, the scheduled value, and a percentage of the total. Lines that are too coarse, like a single line for all of Division 09, make it hard to bill accurately. Lines that are too fine, hundreds of them, turn the pay app into a data entry job nobody wants to own.

The structure that holds up in practice groups work by trade and by phase. Sitework and foundations go near the top because they happen first. Finishes and commissioning go last because they happen at the end. Each line should be large enough to bill against within the first one or two pay apps if it finishes early, but not so large that one line dominates the contract and skews the percentage complete for the whole job.

How to Build One, Step by Step

Start from the approved estimate, not from the contract summary. Pull the line items by spec division, then collapse the detail into billable chunks. For each chunk, ask whether you can measure its progress independently. If the answer is yes, it is a line. If you would have to guess at percent complete, split it further or combine it with something that finishes on the same schedule.

For every line, set a scheduled value that matches the work in it. Add a small contingency line, labeled as such, rather than hiding contingency inside other lines. Hiding contingency is how contractors get asked to justify money they already spent. A visible contingency line is honest and protects you when a line runs over.

Include separate lines for stored materials, general conditions, and profit and overhead, or bury them in the trades, but pick one approach and stay consistent. Most owners and architects prefer overhead and profit spread across the trade lines rather than called out as their own line, because a standalone profit line billed early looks like front loading. Spreading it out keeps the percentage complete on each line tied to real field progress.

Front Loading and Why It Gets You Caught

Front loading is the practice of shifting value into early lines so the contractor gets paid more before the work is done. Some of it is defensible, because mobilization and procurement really do cost money up front and the cash flow has to work. Aggressive front loading is not. When the early lines are priced above their real cost and the later lines are discounted to balance the total, the owner and architect can read the schedule and ask you to revise it. A clean SOV, where each line reflects the real cost of the work in it, is also the one that survives scrutiny.

The test is simple. If a line finished tomorrow, would the scheduled value for it cover the cost of the work plus a fair share of overhead and profit? If the answer is yes for every line, the schedule is honest. If you have to finish three more lines to break even on one, the schedule is front loaded and you will be asked to fix it.

Keeping the Schedule Alive Through the Job

The SOV is not set and forget. As the job changes, change orders add lines or adjust the value of existing ones. Keep a change order log that maps each change to the SOV line it affects, so the total on the schedule always equals the current contract sum. When a change adds work, add a new line rather than burying the value in an existing one, so the auditor can trace the money.

Each month, the pay application reports the previous completed value, the current completed value, and the percent complete for each line. The percent complete should come from field measurement, not a guess. A line that is 90 percent complete in the schedule but only 60 percent done in the field will catch up to you at the end of the job when you run out of money to finish.

Putting It Together

A schedule of values is a contract within the contract. It commits the contractor, the owner, and the architect to the same definition of progress before the first dollar moves. Build it from the estimate, keep the lines tied to real work, avoid front loading, and maintain it as the scope changes. Done well, it makes progress billing a routine. Done poorly, it becomes the most argued document on the project. The time you spend building a clean schedule up front is paid back every month for the life of the job.

Estimate faster with CyanBuild

Upload your drawings and get a full takeoff with visual proof — in seconds.

Try CyanBuild Free